Tuesday, September 28, 2010

Rough-In Inspections are Complete!

Yes! And approved!  Except for a very minor adjustment (which won't hold up anything) the inspection went great.  David said the inspector was "impressed" with the mechanicals.  That means we can proceed with closing up the walls without further delay.
Tomorrow all the wall insulation will be installed.
Thursday morning will be an insulation inspection. All the drywall will be delivered and loaded into the house.
Friday drywall will be installed.
After the drywall is loaded on Thursday then the stucco can be finished as well.  The stone order is delayed a little, but that won't really hold anything else up.
I guess we better decide on some paint colors.